Shepparton RSL Club Solar System Installation

Complete Installation of 99.33kW Roof Mount Solar System in Shepparton

The Manager of the Shepparton RSL club contacted several Solar installers to come up with a solution to their high energy cost, because of the limited roof space the only option was a large-scale solar system to relive the club of some of electricity cost.

After collecting the customers interval data from Powercor and modelling the system around the limited roof space we worked out that a 100kW system was enough to relive the club’s energy cost burden by 30%. The system will save the customer in year 1 roughly $31,000. With a return on investment just over 3.7 years.

This investment for the RSL was an easy decision and with the coordination of the RSL General Manager the job was a seamless installation.

RSL Testimonial from the General Manager Grant Tarrant

“At the Shepparton RSL Sub Branch Inc we recently embarked on a Solar Project, gaining multiple quotations and gathering information to assist the Committee and Management in making an informed decision.

Watters Electrical where awarded the contract and from day one it was a seamless transition from no solar to a fully operational system. Watters Management and staff were a pleasure to work with, contactable at all times and their knowledge and willingness to go the extra mile for us was first class. We look forward to working with Watters Electrical on other projects in the future”

Extent of Works

  1. Complete OH&S paperwork and submit safe work method statements for the site works. Submit Solar Pre-Approval documents to Powercor.
  2. Supply and installation of approved solar panels and inverters
  3. Carry out site survey and locate all anchor points for safety harnesses. Install all mounting rail and tilt bracket framing for solar panels.
  4. Install cable tray and Photovoltaic panels at optimum angle
  5. Install solar inverters and Grid Protection Relay near switchboard
  6. Carry out connections within switchboards & control cabinets.
  7. Carry out final commissioning and shutdown procedure testing.
  8. Arrange for solar system to be inspected by ESV inspector.
  9. Complete paperwork and certificate of electrical safety.
  10. Complete final site clean-up and re-instatement of surfaces to original condition.
  11. Complete As-Installed drawing and Operation and Maintenance Manuals.
  12. Submit all documents to Powercor for solar system connection to grid.

Project Information

Start Date
8th July 2019

Completion Date
22nd July 2019

Project Type
Roof Mount Solar Installation Shepparton

Location
Shepparton VIC 3630, Australia

Solar Hardware Installed

  • 5 x Fronius Symo 20.0-3 (SYMO 20.0-3-S) Inverters
  • 258 x 385-Watt SunPower Solar Panels